2022 Capital Projects

2022 Major Capital Infrastructure Improvement Projects 


Baker Run Stabilization Project:  Project location is between State Street and Westerman.  Project is to remove debris from the banks and stabilize the stream. Project is currently in design and is expected to be constructed in October of 2022.

Baker Run @ Buhl Farm Drive Pipe Replacement Project:  Project is to replace deteriorated storm pipe with new storm pipe.  Pipe has been replaced by J&T Paving, and all restoration has been completed.

Bobby Run MS4 Streambank Stabilization Project:  This is a MS4 required project to mitigate a section of an impaired stream.  Project is to stabilize a 1,200’ section of Bobby Run near Longview Road.  Project has been awarded to Meadville Land Service, Inc. Project has started in late August and is expected to take 12-15 weeks to complete.

Capital Paving Program

The project is to mill off old pavement and repave Easton Road (State Street to Pleasant Drive), Alma Ave., Revere Drive and Ridgelawn Drive. Project has been awarded to G.O. Hawbaker, Inc. and milling of the roadways are to be completed the week of September 26th.  Paving will occur in October.  Signs will also be updated on all these roads.

 

CDBG Paving and Stormwater Project:  Project is to pave Concord Road and Trace Street (Concord to Meadowbrook) in the spring of 2023 and to install stormwater pipe and catch basins on Meadowbrook (State Street to Trace), Concord and Trace (Meadowbrook to Concord) in the Fall of 2022. 

    

Golden Run Pipe Replacement Project: Project is to replace deteriorated pipe at Golden Run LaneProject has been awarded to International Excavating of Ohio, Canfield, Ohio. Project is currently under construction.

 

2023 Neighborhood Investment Program Project:  Project location is S. Crescent Drive (King Street to State Street) and Greenwood Avenue (Trace to State Street).  Project is to mill and pave roadway and install new storm sewers along each side of the road.  Project is currently in design and expected to be constructed in the spring of 2023.

 

Tenth Street Road Improvements:  Through an agreement, the City of Hermitage and the City of Sharon will be paving Tenth Street (George Street to Charles Street).  Project has been completed.

 

PA DOT Highland Road Project:  The PA DOT Department of Transportation has contracted Lindy Paving to mill and pave Highland Road from N. Hermitage Road to Forker Ave.  Work has started the week of July 11th and is expected to be completed in October.  Paving has been completed and pavement markings are currently being applied by the contractor.