Home > City Government > City Projects

CURRENT CONSTRUCTION PROJECTSHunter's Woods
Stormwater Improvement Project
· Location
: Route 18, near Hermitage Vet and Northstar Power Sports
· Project
: Construction of stormwater detention facility and drainage improvements to
improve drainage issue in the immediate area.
· Status /
Schedule : Construction work began in January 2011 and is scheduled to be
complete in late spring. David Construction Co. - Hermitage, PA
More Info
North Buhl Farm Drive Pedestrian Improvements
Project
· Location
: N. Buhl Farm Drive between E. State St. & Highland Road - N. Buhl Farm Drive /
Hazen Road
· Project
: Construction of sidewalks on the west side of N. Buhl Farm Drive, intersection
improvements to Theota Dr / N. Buhl Farm Drive, and intersection
improvements/pedestrian facilities at Hazen Road / N. Buhl Farm Drive
intersection. Aqua PA water line upgrades.
· Status /
Schedule : Construction work began March 18, 2011 and is scheduled to be
complete in June 2011. Combine Construction Co. - Sharon, PA
More Info
Woodside Drive & Connecting Streets - Roadway and
Stormwater Improvement Project -
Neighborhood Investment Program
· Location
: Woodside Dr, Lyle Dr, Cohasset Dr, Richmond Dr & Pine Tree Lane
· Project
: Roadway paving and stormwater improvements. Aqua PA water line upgrades.
· Status /
Schedule : Construction work will begin in early April 2011 (Aqua PA water
line work began in March 2011). Project is scheduled to be complete in
Fall 2011. David Construction Co.
More Info
Rombold Road Area - Roadway & Stormwater
Improvements Project -
Neighborhood Investment Program
· Location
: Rombold Road, Haywood St, Mary St, Paul St, Madison St, Carolyn St, Stafford
St, Delaware
· Project
: Roadway paving and stormwater improvements.
· Status /
Schedule : Paving will take place beginning in June 2011 and work will be
complete by September 2011. United Civil Contractors, David Construction Co.,
TBD
More Info
Maple Drive / Dutch Lane / East State Street
Intersection Improvement Project
· Location
: Maple Drive / East State Street
· Project
: Add dedicated left turn lane on Maple Drive northbound, new pavement,
pedestrian facilities and traffic signal facilities.
· Status /
Schedule : Work began in September 2010, w/ majority of roadway work
complete. Remaining work includes new traffic signals / mast arms and
final restoration. Kirila Contractors
More Info
CAPITAL INFRASTRUCTURE / TRANSPORTATION PROJECTS
· Neighborhood
Investment Program (NIP) NEW
Information Posted
· Indian Run Stream Restoration - Phase III
· 2011 Capital
Paving / Seal Coating Program
· 2008 - 2011 CDBG Stormwater
and Roadway Improvements NEW
Information Posted
· Maple Drive / Dutch Lane / East State Street Intersection Improvements Project NEW
Information Posted
· Lamor Road Improvement Project
· North Buhl Farm Drive Corridor Project (Elm Street
Program)
NEW
Information Posted
· Hermitage Municipal Authority (Sewer) Projects
· Hunter's Woods
Stormwater Improvement Project NEW
Information Posted
RECREATION PROJECTS
· Whispering Pines Park (East State Street)
· Linden Pointe Phase II Trails
· Hermitage
Athletic Fields Complex Project - South Darby Road
· Timber Lane / Silver Ridge Trail Project
· Sylvia Stull Farmstead Property (Sample Road)
· Buhl Park Casino Renovation Project
ECONOMIC DEVELOPMENT PROJECTS
· LindenPointe Training & Workforce Development
Building
·
LindenPointe Technology Center & Business Incubator
PLANNING PROJECTS
· Shenango
Valley Multi-Municipal Comprehensive Plan
· Hermitage Town
Center Study
Following is a brief summary on the status of the active projects:
·
Neighborhood Investment Program
New Information Posted! BLOCK 1
MARCH 9,
2011 - Hermitage firm awarded contract for street work
Hermitage commissioners on Tuesday awarded a contract for road
construction and storm water drainage improvements in the Woodside Drive area to
David Construction Co. Inc., Hermitage. The company’s bid, $816,304, was the
lowest of 10. The pre-bid estimate was $1.1 million. Work will be done on
Woodside from Boyd Drive to Lyle Drive; Lyle from Woodside to Highland Road;
Richmond Drive from Woodside to Highland; Cohasset Drive from Woodside north to
the cul-de-sac; and Pine Tree Lane. New signs will be put up and the company
will try to minimize traffic disruptions, Hinkson said. “We are going to try to
keep the streets open,” he said. “There might be some periodic adjustments in
traffic flow.” Officials hope the work will be done in the fall.
February 23, 2011 - Engineer : Street, Basin Bids Come In Under Estimates
It
is one of the core functions of local government to provide and maintain a
functionally sound infrastructure system. It is the City’s responsibility to
invest in our community to protect the integrity of our neighborhoods. To do
otherwise, or to neglect the infrastructure – sanitary sewer lines, storm water
facilities, street paving, lighting and signage will lead to neighborhood
blight, depressed property values, a reduction in the quality of life for
residents and higher costs when improvements are eventually undertaken.
The objective of the Neighborhood Investment Program is to systematically
upgrade the City infrastructure, an area at a time in our older, established
neighborhoods before deterioration begins. We will do so by identifying the
program areas, taking a comprehensive assessment of existing conditions
including input from property owners and residents, determining needs and
developing a work plan, funding sources and a timeline.
The impact of a public/private partnership, where property owners work with the
City – the City upgrading and improving public facilities and the residents
continuing to maintain, or improve, their properties, will result in maximized
property values and a high quality of life in our neighborhoods.
2008 - 2011 Work Program
Neighborhood included bounded by:
Highland Road (North), N. Buhl Farm Drive (East), State Street (South) & Boyd
Drive (West)
Back to Top

· Indian Run Stream Restoration Phase III – Indian Run
Stream Restoration – Approximately 1,800 linear feet of Indian Run between
Route 18 extending west and north behind the Hermitage Elementary School will be restored using Natural
Stream Channel Design techniques. The project will create new floodplain and riparian buffers, which
will be planted with grasses, shrubs and trees. The newly created floodplains will
assist in the reduction of flood waters, and in conjunction with the riparian
buffer will help prevent erosion by stream bank stabilization, reduce non-point
source pollution and enhance aquatic habitat. The project is being designed by Wallace & Pancher, Inc. of Hermitage, PA
and is planned for construction in late 2010. The City received a
Growing Greener II Grant from the Department of Environmental Protection in the
sum of $95,000 for construction of the project.
Phase I : School Project completed in 2004
Phase II : Completed Summer 2007
Phase III : Scheduled for construction in 2010 (RT 18 – School)
July 29, 2010 - Low Bidder Out, 2nd Gets Contract (Indian Run Phase III)
August 24th, 2010 - Construction begins on Indian Run Phase III.
Construction is planned to take place until mid-October, with plantings and
final restoration completed shortly after.
Construction photos - September 2nd, 2010


Hermitage School District's "GREEN TEAM" takes part in Indian Run Project.
Thanks to the volunteers for all their help!


Construction Photo - November 1st, 2010

Back to Top

· 2011 Capital Paving
Program
Streets to be determined.
Back to Top

· 2008-2011 CDBG
Stormwater and Roadway Improvements (Neighborhood Investment Program) - Rombold
Road area - Census Tract 311 - Block Group 2.
March 31st, 2011 - Low bid
comes in under estimate to pave roads
HERMITAGE — A Wampum company submitted the apparent low bid to pave streets
in the Rombold Road area of Hermitage. Youngblood Paving Inc.’s bid of $307,135
was the lowest of six opened Wednesday. Engineer Herbert, Rowland and Grubic
Inc., Hermitage, had estimated the work would cost $330,000 and the other bids
ranged from $324,510 to $364,199. The project calls for paving Rombold, Delaware
Street and the parts of Haywood, Mary, Paul, Madison, Carolyn and Stafford
streets in Hermitage. City commissioners likely will award a contract in April.
This project will complete a three-phase, two-year program of storm water
drainage improvements and road repairs in the area with the use of federal
Community Development Block Grant funds.
Phase I was completed in
August 2010, this included stormwater infrastructure work on Rombold Road from
Mercer Ave. to Madison Ave.
Work began on Phase II in the Fall of 2010.
This work will include the remainder of the stormwater infrastructure work on
Rombold Road and pavement work on Rombold Road, Haywood, Mary, Paul, Madison,
Carolyn, Stafford & Delaware.
September 18, 2010 - Rombold Road Fix-Up Cost Less Than Expected
Back to Top

· Maple Drive / Dutch Lane / East State Street Intersection Improvements Project
Construction of a left turn lane on Maple Drive, sidewalks, and traffic signal improvements.

$533,000 (80% Federal,
20% Local) - This project is scheduled to begin construction late-Summer 2010.
July 29, 2010 - Construction Nears on Widening of Maple Drive
PROJECT UPDATE: September 22nd, 2010
The Maple Drive Improvements Project began construction on
Tuesday, September 7th, 2010. The project includes adding a dedicated
left turn lane to Maple Drive on the south side of East State Street, new
sidewalks, curb ramps, mast arms, signals and cross-walks. The majority of
the construction activity will take place from mid-September through the end of
October. New traffic signals and mast arms will be installed this fall.
The project is schedule for final completion by April 2011.
No road closures are planned for the construction project and all lanes should
remain open throughout construction, with temporary lane closures as needed.
Contractor: Kirila Contractors, Brookfield OH
Construction Photos:


Back to Top
· Lamor Road Improvement Project

Status: Construction is complete
Project Cost: $600K (approx.)
(ARRA - Federal Stimulus Project)
Project Update - June 16, 2010
Lamor Road opened to traffic on Friday, June 11th.

Jason Kapusta/ Sharon Herald - April 21, 2010
Part of Lamor Road, between North Hermitage Road and Joy Cone Co., in Hermitage
has been closed for a widening project that includes adding a center turn lane.
Detours have been posted. Other work includes adding new curb gutters and
sidewalks accessible to the handicapped, and improving drainage.
Back to Top
· North Buhl Farm Drive Corridor Project (Elm
Street Program)

The City has received a $500,000 grant from the Pennsylvania Elm Street Program
to make improvements to the North Buhl Farm Drive Corridor.
These improvements are planned for 2010-2011 and would include sidewalk construction,
intersection improvements and other related pedestrian facilities.
Work began in March 2011 with completion scheduled by
June 2011.

Construction on Hazen Road @ N. Buhl Farm Drive intersection (April 15, 2011)
NORTH BUHL FARM DRIVE PEDESTRIAN IMPROVEMENT PROJECT - CONSTRUCTION UPDATE
Due to upcoming construction activities along North Buhl Farm Drive in the
City of Hermitage, the west side of North Buhl Farm Drive (southbound traffic),
from East State Street – Highland Road, will be closed, weather permitting, on
Friday, March 18th, 2011 through June 1, 2011 (approx.). Construction includes
building sidewalks and water line replacement. Detours and signage will be in
place during construction

Sharon-Herald - Wednesday, March 23rd, 2011
The southbound lane of North Buhl Farm Drive is closed to traffic as
workers from Combine Construction Inc. replace water lines. A detour forces
drivers to travel east on Highland Avenue..
November 11, 2010 - Combine Construction Gets Sidewalk Contract
Back to Top
·
Hermitage Municipal Authority (Sewer) Projects
PUBLIC NOTICE -
03/17 - ADVERTISEMENT FOR BIDS - Pine Hollow Blvd. Sewer Improvements - Bids Due
April 20th @ 10AM

February
4, 2011 - Electrical Service Work Swells Costs

February 2, 2011 - $32M Treatment Plant Project Underway

January 6, 2011 - Shale Shelf Will Reduce Costs

November
4, 2010 - Short Sewer Line Extension Sought

October
7, 2010 - Plant Contracts Ok'd; Authority Waits on DEP

Daniel Drive Extension Project (2008) - $510k
Magargee Run Project (Hermitage / Jefferson Township) 2009 - $670k
Hermitage WPC Treatment Plant Expansion Project (2009-2012) - $31M
Collection System Improvements (ongoing) - $45k
Back to Top
·
Hunter's Woods Stormwater Improvement Project
Contract awarded to David Construction, Hermitage, PA
Work began in January 2011 - $300K(appx.) project cost

February 2nd Construction Photo
March 21st Construction Photo

December 4, 2010 - Hunter's Woods Storm Basin Contract Awarded
Back to Top
·
Whispering Pines Park – Phase I of this community park
is now complete. Adjacent to the Hermitage Historical Society and across from
the Hermitage VFW along East State Street, it consists of a parking lot,
restrooms, open play area and approximately 1/2 mile of paved trails with an
additional 1/2 mile of unpaved, grass trail. Pedestrians can also access the
trails and park from a point along North Darby Road. The trails combine both
open areas and beautiful wooded areas in the 22 acre park.
Back to Top
·
LindenPointe Phase II Trails – Phase II of the trails
at the LindenPointe Innovative Business Campus is now complete and open for
public use. Parking is available in two lots, one off Christy Road and the
adjoining lot that is accessible from Innovation Way. Pedestrians can access the
trails at points along Christy Road, South Hermitage Road and Emilie Lane. There
are now over 1.5 miles of paved trails winding through open and wooded areas of
the campus. The City received a $100,000 grant from the Pennsylvania Department
of Conservation and Natural Resources for trail construction, and the City also
received a Pennsylvania Department of Community and Economic Development grant
in the sum of $8,000 for trail improvements, such as the purchase and
installation of benches and trash receptacles.
Back to Top
Hermitage Athletic
Fields Complex Project - South Darby Road

The
proposed City of Hermitage Athletic Complex will help to satisfy the immediate
need for additional sports facilities. The City’s initial program for the
Complex was for two girls’ softball fields and multi-use fields with one being
suitable for competitive games. The program of uses was further expanded to
include the necessary support uses for the athletic fields as well as passive
and active uses attractive to a variety of age groups. The additional program
elements include:
1. A concession stand and restrooms;
2. Informal gathering and picnic areas;
3. Play ground areas adjacent to the fields;
4. Walkways and trails; and
5. Sufficient parking to accommodate consecutive events during the
playing season.
The City intends to build first phase of this project utilizing local bond issue
dollars issued in 2005. The approximate cost of Phase I is $1.5 million.
City officials have completed the master plan and preparing to go out to bid for
project construction, excepted in the spring of 2009.
Future phases will be built later based on the availability of funding.
Construction is
complete as of August 2010.
The City is now in the process of formulating a maintenance and operational plan
for the Complex. Field will be ready for use in spring 2011. Look
for more details to come in the near future.
Back to Top
· Timber Lane / Silver Ridge Trail Project

The project is intended to create a pedestrian connection between the two
neighborhoods through the construction of a walking path on two undeveloped
parcels of land. The project has a $20,000 budget ($5,000 of which is
grant funded) and was started in late 2008. The project is complete.
Back to Top
· Sylvia Stull Farmstead Property (Sample Road)

Sample Road, 40 acres - Bequeathed to the City by former City Board of
Commissioners member Sylvia Stull. The City is currently in the process of
planning and taking public input on the future use of this property.
Back to Top
· Buhl Park Casino Renovation Project

Buhl Park received approximately $1.25M in grant funding through the State and
Federal government to complete renovations to the Buhl Farm Park Casino
Building. Total Project Cost : $2.5 M Project construction is scheduled
for 2009-2010.
November 4, 2008
Press Release -
$750,000
state grants come through for the Buhl Park Casino project - City received
$500,000 in state funds for North Buhl Farm Drive Corridor Project
May 21, 2009
Press Release -
State Rep. Mark Longietti announces $500,000 in additional state funding for
Buhl Park Casino Renovation Project
Back to Top
· LindenPointe Training & Workforce
Development Building

Construction is complete.
More information @ www.lindenpointe.com
Back to Top
· LindenPointe Technology Center &
Business Incubator

Construction began in June 2010 and is schedule for completion in September
2011.
More information @ www.lindenpointe.com
Back to Top
· Shenango Valley Multi-Municipal Comprehensive Plan
The Shenango Valley municipalities of the City
of Sharon, City of Hermitage, City of Farrell, Wheatland Borough, West Middlesex
Borough & Shenango Township, with assistance from Spotts, Stevens, McCoy, Inc.
and the Mercer County Regional Planning Commission, are in the process of
developing a multi-municipal comprehensive plan for the region.
Two multi-municipal comprehensive plans will be prepared in this planning
process. One plan will focus on Farrell City, Hermitage City, Sharon City, and
Wheatland Borough. The second plan will focus on West Middlesex Borough and
Shenango Township. Both plans will be coordinated with each other and with a
multi-municipal comprehensive plan recently completed for the Boroughs of Clark
and Sharpsville and the Township of South Pymatuning, so as to result in
coordinated planning for the greater Shenango Valley region.
Click here for more details.
Draft
Plan available for viewing (MCRPC link, 43MB) October 2007
Back to Top
· Hermitage Town Center Study
The Hermitage Town Center Study is a community-based planning project, sponsored by the Mercer County Regional Planning Commission and the City of Hermitage. The goal of the project is to develop a master plan for the area that will lead to the establishment of a memorable town center for the City of Hermitage; one that creates a unique identity based on a walkable, mixed-use community. The project is focused on the intersection of Rt. 18 and Rt. 62 (State St.), but will extend out beyond that to include to a wider area in an effort to foster connections to the surrounding neighborhoods. The project was funded by the Pennsylvania Department of Transportation as a follow-up to the Rt. 18 North Study completed in 2001 that preceded the widening of the road through the City of Hermitage.
Click here to view the
full report.
The Hermitage Town Center Study (w/addendum) was accepted by the Board of
Commissioners at their March 26, 2008 meeting.
Back to Top
City of Hermitage, 800 North Hermitage Road, Hermitage, Pennsylvania 16148
Phone: 724-981-0800. Fax: 724-981-2008. www.hermitage.net
All listings and artwork are Copyright © 2010 by City of Hermitage or links. Disclaimer
|